After a very successful first month of April, life at the pub is continuing. New management has settled in and the building has welcomed them with open arms. Of course that does not mean that the building isn’t always in need of attention. It’s old and needs TLC on a rolling basis.
So this month we are refurbishing the potwash, cold store and corridor. All to ensure that service is tip-top. We start the month of May with the May Bank Holiday over the course of 1-4th of May. The weather will hopefully support sunny days in the garden. With a special Bank Holiday ‘blow-out’ on May 4th.
Then, on May 10 and 11 , the potwash area is being prepared for the floors to be renewed. We will fit stainless steel panels to the wall for easy wipe-down and protection. This work will happen on the Sunday evening and all day on Monday so that normal service hours are not affected.
Then, the week after that, on May 17/18, the floors will go in to make sure that everything is fully op-to-spec. The current floors have some cracks that need to be repaired.
All this work is being supported by local trades and volunteers. Flooring, Builders, Plumbers, Residenst of Horningsea – You know who you are! The CIC thanks everyone who is working hard and making time in their schedules. It is very much appreciated.
So here’s the schedule:
- 3/4 May: May bank Holiday weekend – Come visit!
- 10/11 May: Prep work to make ready for flooring
- 17/18 May: Fit flooring